AI-DLC State Tracking

Project Information

  • Feature Name: CMS Frontend
  • Feature Slug: cms-frontend
  • Project Type: Brownfield
  • Start Date: 2026-06-16T20:27:00Z
  • Current Stage: CONSTRUCTION - Unit 2: Authentication Pages — COMPLETED
  • Branch: unknown

Workspace State

  • Existing Code: Yes (.NET API backend + example React app in ZIP)
  • Reverse Engineering Needed: Yes (shared reverse engineering for backend; example app analyzed)
  • Workspace Root: K:\Development\Projects\SlpModularCms

Code Location Rules

  • Application Code: frontend/ (new Vite + React app; kept outside src/ to keep the .NET solution clean — see unit-1-code-generation-plan.md)
  • Feature Documentation: aidlc-docs/features/cms-frontend/ only
  • Shared Artifacts: aidlc-docs/_shared/
  • Structure patterns: See code-generation.md Critical Rules

Language Configuration

  • Documentation Language: English
  • Conversation Language: Dutch (nl)

Extension Configuration

Extension Enabled Decided At
Security Baseline Yes Requirements Analysis
Property-Based Testing No Requirements Analysis

Execution Plan Summary

  • Total Units: 6
  • Stages to Execute: Application Design, Units Generation, Functional Design (per unit), NFR Requirements (Unit 1), NFR Design (Unit 1), Code Generation (per unit), Build and Test
  • Stages to Skip: Infrastructure Design (no cloud infra; static SPA)

Stage Progress

🔵 INCEPTION PHASE

  • Workspace Detection — Completed 2026-06-16T20:28:00Z
  • Reverse Engineering (shared) — Completed 2026-06-16T20:32:00Z
  • Requirements Analysis — Completed 2026-06-16T21:00:00Z
  • User Stories — Completed 2026-06-16T21:05:00Z
  • Workflow Planning — Completed 2026-06-16T21:15:00Z
  • Application Design — Completed 2026-06-16T22:00:00Z
  • Units Generation — Completed 2026-06-16T22:20:00Z

🟢 CONSTRUCTION PHASE (per unit)

  • Unit 0 — Backend Prerequisites (CORS + httpOnly cookie) — COMPLETED 2026-06-19T11:45:00Z
  • Unit 1 — Project Scaffold & Infrastructure — COMPLETED 2026-06-20T17:30:00Z
  • Unit 2 — Authentication Pages — COMPLETED 2026-06-21
  • Unit 3 — Layout & Navigation
  • Unit 4 — Dashboard
  • Unit 5 — User Management
  • Unit 6 — Profile, Settings & CMS Placeholder
  • Build and Test — Not Started

🟡 OPERATIONS PHASE

  • Operations — Placeholder